Construction is progressing! Here is a look-ahead schedule for the next six weeks (October 25-December 5):

House:

  • Demolition of interior walls continues; then interior framing will begin

Addition:

  • Excavation and backfilling for foundations continues
  • Work on foundation begins
  • Begin work on the elevator shaft

Main Library:

  • The walls have been opened

Questions? Email Marcy at development@cfplcorp.org or call 617-869-1268