Construction Updates

Construction Updates

Construction is progressing!

House:

  • Framing for elevator underway
  • Continuing work in the attic
  • Continuing rough-in for multiple trades

Addition:

  • Foundation work: finish excavation for deep foundations
  • Continue to form; pour; damp-proof and insulate foundations.
  • Plan is to finish foundation work by the end of December.

Library:

  • Planning for cutting a door opening into the vault in Special Collections

Questions? Email Marcy at development@cfplcorp.org or call 617-869-1268

In case you missed it, watch the Project Update (from 12/10) now