Construction Updates Copy

Construction Updates

Construction is progressing!

House:

  • Exterior walls done; continuing stair 2
  • Rough in for various trades continues

Addition:

  • Continued work on foundation and final footings
  • Structural steel and decking continues
  • Slab rough in next week

Library:

  • Work in vault by various trades will start next week

Questions? Email Marcy at development@cfplcorp.org or call 617-869-1268